Current stage of the construction works as of 30.09.2019

Current stage of the construction works as of 30.09.2019

Following works have been realised within the infrastructure component of the project as of September 30th, 2019:

  • Construction works – Demolition, earthworks and preparatory works – 47,5% ,
  • Landscaping – 24,7%, (including trees reclamation, trunks protection etc.),
  • Storm drain, culverts, culverts under the ramps – 65 % ,
  • Substructure, widening – 14,6 %
  • Telecom engineering collisions – 100%
  • Sanitary (water pipeline) – 75,3%
  • Reconstruction of Power lines (collisions) – 90,2%