Current stage of the project implementation as of December 31st, 2019

Current stage of the project implementation as of December 31st, 2019

Current stage of the project implementation as of December 31st,  2019:

  • Construction works – Demolition, earthworks and preparatory works – 69,8% , Substructure – 46,3%, (including rubblising till 24.11.2019 – 51% and till 30.11.2019 – 100%) , Berms, curbstones, surface – 6,8%, Storm drain, culverts, culverts under the ramps – 65 % , Substructure, widening – 14,6 %  ;
  • Telecom engineering collisions – 100%;
  • Sanitary (water pipeline) – 75,3%;
  • Reconstruction of Power lines (collisions) – 90,2%, lighting lines – 10,2%;