Current stage of the project implementation as of December 31st, 2019:
- Construction works – Demolition, earthworks and preparatory works – 69,8% , Substructure – 46,3%, (including rubblising till 24.11.2019 – 51% and till 30.11.2019 – 100%) , Berms, curbstones, surface – 6,8%, Storm drain, culverts, culverts under the ramps – 65 % , Substructure, widening – 14,6 % ;
- Telecom engineering collisions – 100%;
- Sanitary (water pipeline) – 75,3%;
- Reconstruction of Power lines (collisions) – 90,2%, lighting lines – 10,2%;