Current stage of works

Current stage of works

Current stage of the construction works as of April 9th 2020 was following:

  • Construction works: demolition, earthworks and preparatory works – 88,77 % of contracted scope; Landscaping (including trees reclamation, trunks protection etc.) – 24,7% of scope; Storm drain, construction of water supply and sewage pipelines – 73,36%; substructure, widening – 91,52 %; Installation of curbs and road fringers – 43,34%
  • Permanent organization of road traffic: Dismantling and installation of the road signs – 0,54%;
  • Telecom engineering collisions removal – 100%;
  • Sanitary underground (water pipe) – 75,33%;
  • reconstruction of the power lines (collisions removal) – 98,95% of the scope prescribed in the construction works contract.

The works had been supervised by Investor’s supervision (ZDI Sp. z o.o.) and by the Project Manager, responsible for infrastructure component of the project.

Also subcontractors and their contracts realisation was supervised by Project Manager.