Schedule

Current stage of the project implementation as of December 31st,  2019:

  • Construction works – Demolition, earthworks and preparatory works – 69,8% , Substructure – 46,3%, (including rubblising till 24.11.2019 – 51% and till 30.11.2019 – 100%) , Berms, curbstones, surface – 6,8%, Storm drain, culverts, culverts under the ramps – 65 % , Substructure, widening – 14,6 %  ;
  • Telecom engineering collisions – 100%;
  • Sanitary (water pipeline) – 75,3%;
  • Reconstruction of Power lines (collisions) – 90,2%, lighting lines – 10,2%;

 

 

Current stage of the construction works as of 30.09.2019

Following works have been realised within the infrastructure component of the project as of September 30th, 2019:

  • Construction works – Demolition, earthworks and preparatory works – 47,5% ,
  • Landscaping – 24,7%, (including trees reclamation, trunks protection etc.),
  • Storm drain, culverts, culverts under the ramps – 65 % ,
  • Substructure, widening – 14,6 %
  • Telecom engineering collisions – 100%
  • Sanitary (water pipeline) – 75,3%
  • Reconstruction of Power lines (collisions) – 90,2%